Tule Wind Energy Project
CACA-49698
Environmental and Construction
Management
Compliance Monitoring Program
Welcome to the Environmental and Construction Compliance Monitoring Program website for the Tule Wind Project. The Bureau of Land Management (BLM) issued a Record of Decision approving the project on December 19, 2011 and issued the right-of-way (ROW) grant on
April 10, 2012.
An Environmental and Construction Compliance Monitoring Program (ECCMP) was prepared for the project. The plan addresses the requirement to develop an environmental and construction monitoring plan for the project covering both construction and operation. This site has been established to track construction and monitor progress and completion of the mitigation goals established in the project's Environmental Impact Statement (EIS) and stipulations in the ROW grant.
Background
Construction Progress and Environmental and Construction Compliance Reporting
Notices to Proceed
Environmental Monitoring Reports
Variance Requests
Related Links
Tule Wind LLC was issued a BLM ROW Grant for wind testing and
monitoring at the proposed Tule Wind Project site in
southeastern San Diego County on September 15, 2004. Tule Wind
LLC submitted an amended ROW application to the BLM for the
development of an energy generation facility on December 21,
2007. On April 10, 2012, the BLM issued a ROW grant to Tule Wind
LLC to construct, operate, maintain, and decommission a 186
megawatts (MW) wind energy project (Tule Wind Project) and its
ancillary facilities on 12,360 acres of public land. The project
components to be developed on public lands include 62 wind
turbines, a 34.5 kilovolt (kV) overhead and underground collector cable system, a 138 kV transmission line, a meteorological tower, and access roads. The Tule Wind Project when complete will connect to the Boulevard Substation rebuild component of San Diego Gas & Electric’s (SDG&E’s) East County (ECO) Substation Project.
The BLM, in conjunction with Tule Wind LLC drafted an Environmental and Construction Compliance Monitoring Plan (ECCMP) to ensure compliance with mitigation measures approved in the Final EIS, as well as with the terms and conditions associated with the BLM right-of-way grant. Although changes may be made to the document as construction progresses, a current version of the ECCMP document and attachments is found here. The regional map and project location map depict the location of the project.
Back to Top
Issuance of NTPs will be contingent upon Tule Wind LLC’s compliance with pre-construction requirements as specified by the approved mitigation measures and responsible agency permitting requirements. Approved pre-compliance reports, permit applications, and other documents are available in their final form here. NTPs that have been issued to Tule Wind LLC are noted in the table below.
| Notice to Proceed |
Construction Activities |
NTP Request Submitted |
NTP Issued |
| 1 |
Geotechnical Investigation |
April 10, 2012 |
September 17, 2012 |
| 2 |
Civil Construction |
Pending |
Pending |
| 3 |
Foundation Construction |
Pending |
Pending |
| 4 |
Electrical System |
Pending |
Pending |
Back to Top
A BLM Environmental Monitor (EM) will monitor construction activities to ensure that they are conducted in accordance with the approved mitigation measures and permit conditions. Monthly reports documenting construction status and compliance activities are posted here.
Back to Top
As defined by the ECCMP, at various times throughout project construction, the need for extra workspace or additional access roads may be identified. Similarly, changes to the project requirements (e.g., mitigation measures, specifications, etc.) may be needed to facilitate construction or provide more effective protection of resources (e.g., installation of additional erosion control outside of approved disturbance areas). The BLM Project Manager, along with the BLM EMs, will implement the variance procedures defined in the ECCMP to evaluate each proposed project variance for its potential for creating adverse environmental effects to determine whether supplemental NEPA review is required. Variance requests are posted here.
Back to Top
BLM Tule Wind Project
Tule Wind LLC
California Public Utilities Commission ECO Substation Project
San Diego County
Back to Top
This website is being hosted by Dudek and is not an official BLM website. This page contains tables and is
best viewed with Netscape or Internet Explorer. Please report any problems to
the web
coordinator.
|
CONTACT INFORMATION
Compliance Monitors
800-735-0848
tulewindeccmp@dudek.com
(10MB attachment limit)
BLM El Centro
Brian Paul
1661 S. 4th Street
El Centro, CA 92243
Phone: 760-337-4400
Fax: 760-337-4490
Email: rpaul@blm.gov
PDFs on this site require Adobe Acrobat Reader. It may be downloaded for free here.
This site is managed by Dudek, the environmental compliance monitor.
|